We have put our District information online to provide convenience, online services and information sharing.  On our site, you'll find a community calendar, Board meeting schedules, agendas and minutes, news and announcements.  In our Resource Center, you'll find such things as financial information and important documents and forms.

We are very excited about offering online services and consider this to be a valuable amenity for the community.    

Concrete Updates

Concrete Project Update - 11/23

All concrete areas in the scope of this replacement project have now been poured. However, the project is not done until the remaining cleanup, repair, and caulking steps have been completed. A brief summary of next steps is below, with more information coming next week after the Thanksgiving holiday.

  • Landscaping Cleanup & Repair: Landscaping impacted by the concrete work in all areas will be repaired over the next few weeks. This work has started on the west half of Depew Street.
  • Downspout Repair: Downspouts impacted by the concrete work in all areas will be repaired over the next several weeks. This work has not yet started.
  • Caulking: Final touch caulking will continue over the next few weeks. The work has mostly finished on the west side of WLV and is now starting on the east side of Depew Street. Plastic dividers between your garage and a driveway or alley will be removed and replaced with caulking.
  • Power Washing & Paint Issues: The superintendent is currently working with the developer to put together a plan to address paint-related issues caused by the concrete work. More information will be shared next week.
  • Staging Areas: Any signs, cones, etc. currently in a staging area will be removed by the end of next week.

Concrete Schedule Update - 11/18

  • Areas 7 (non main alley), 8, & 9: Most of these areas were poured yesterday (11/17), and the remaining sections will be poured today (11/18) due to an unexpected issue encountered yesterday with a broken utility line. Garage access is expected to be available again on Saturday (11/20), while sidewalks and front stoops are okay to walk on 24 hours after the concrete has been poured. Please do not step on the blankets covering the concrete - these blankets are in place to help the concrete finish curing during the cold weather. 
  • Power Washing, Cleanup, & Caulking: The concrete crew power washes garages and houses after work is complete; please be patient, as this process can take a few days to occur after the concrete has fully cured and is drivable again. Downspouts and landscaping impacted by the concrete work in all areas will also be repaired over the next few weeks. Final touch caulking will take place in the next several weeks and could temporarily impact garage access for a few hours; more details coming on this impact soon.

 

Concrete Schedule Update - 11/16

·  **Depew Street Parking Closures**: All street parking is temporarily closed on the east side of Depew Street between W 10th Place and W 10th Avenue today (11/16) and tomorrow (11/17) from 7 AM to 5 PM to make room for the equipment needed for the concrete work in this area and to avoid damaging parked vehicles. Any vehicles left in this area between 7 AM and 5 PM today or tomorrow will delay the concrete work and potentially extend the street parking closure for everyone, so please be courteous of these temporary restrictions. Additionally, temporary no parking signage has been posted in this area, and the temporary closure areas are also shown on the attached map.

 

·  Areas 7 (non main alley), 8, & 9: Demo has been completed in all of these areas, with a concrete pour scheduled for Wednesday (11/17). Garage access is expected to be available again as early as Saturday (11/20), while sidewalks and front stoops are okay to walk on 24 hours after the concrete has been poured. Please note that soil conditions and/or incoming weather has the potential to impact these timelines - we will continue to communicate updates as they become available.

·  Power Washing, Cleanup, & Caulking: The concrete crew power washes garages and houses after work is complete; please be patient, as this process can take a few days to occur after the concrete has fully cured and is drivable again. Downspouts and landscaping impacted by the concrete work in all areas will also be repaired over the next few weeks. Final touch caulking will take place in the next several weeks and could temporarily impact garage access for a few hours; more details coming on this impact soon.

 

·  Revised Map: Please see attached for a revised map to show this week's work areas as well as the temporary street parking closures on Depew Street.

Concrete Schedule Update - 11/12 - including upcoming Depew Street Parking closures!

  • **Depew Street Parking Closures**: All street parking will be temporarily closed on the east side of Depew Street between W 10th Place and W 10th Avenue on Monday (11/15) through Wednesday (11/17) from 7 AM to 5 PM to make room for the equipment needed for the concrete work in this area and to avoid damaging parked vehicles. Any vehicles left in this area between 7 AM and 5 PM on 11/15 - 11/17 will delay the concrete work and potentially extend the street parking closure for everyone, so please be courteous of these temporary restrictions. Additionally, temporary no parking signage has been posted in this area, and the temporary closure areas are also shown on the attached map.

  • Area 11: Concrete was poured yesterday (11/11), and the goal is to reopen this area to vehicles late Monday (11/15), depending on weather.
  • Areas 8 & 9: Some demo is expected today (11/12) for areas that do not impact garage access. Demolition for areas that will impact garage access will begin on Monday (11/15). A concrete pour for Areas 8 and 9 is tentatively scheduled for Wednesday (11/17) or Thursday (11/18), depending on the results of soil testing and the impact of weather. Garage access is expected to be available again the following Monday (11/22).
  • Area 7 Remaining Areas: There are a few small remaining areas to demo and replace in Area 7 outside of the main alley that was already replaced; these areas will be addressed at the same time as Areas 8 and 9 (see above for timeline).

  • Power Washing, Cleanup, & Caulking: The concrete crew continues to power wash garages and houses after work is complete; please be patient, as this process can take a few days to occur after the concrete has fully cured and is drivable again. Downspouts and landscaping impacted by the concrete work in all areas will also be repaired over the next few weeks. Final touch caulking will take place in the next several weeks and could temporarily impact garage access for a few hours; more details coming on this impact soon.

  • Trash Cans: If your alley is inaccessible due to the concrete work, your trash cans can be set out on 11th or 10th Place (east-west streets) for Waste Management to pick up.
  • Revised Map: Please see attached for a revised map to show the areas of upcoming work next week as well as the temporary street parking closures on Depew Street.

Thanks again for your patience with this project! The concrete crew is working quickly, and if the weather holds, the crew should be able to finish ahead of the original schedule. We will continue to send periodic updates as the work nears completion.

Concrete Schedule Update - 11/11

  • Area 11: Demolition and prep work have both been completed, with a concrete pour planned for today (11/11). The goal is to reopen this area to vehicles late Monday (11/15), depending on weather.
  • Areas 8 & 9: Areas that do not impact garage access may be demoed as early as Friday (11/12) but may start on Monday (11/15) depending on the progress made by the concrete crew today. For areas that will impact garage access, demolition will begin on Monday (11/15) with garage access expected to be available again the following Monday (11/22).
  • Area 7 Remaining Areas: There are a few small remaining areas to demo and replace in Area 7 outside of the main alley that was already replaced; these areas will be addressed at the same time as Areas 8 and 9 next week. 

  • Advance Notice - Depew Parking Closures: All street parking will be temporarily closed on the east side of Depew Street between W 10th Place and W 10th Avenue on Monday (11/15) through Wednesday (11/17) from 7 AM to 5 PM to make room for the equipment needed for the concrete work in this area and to avoid damaging parked vehicles. Any vehicles left in this area between 7 AM and 5 PM on 11/15 - 11/17 will delay the concrete work and potentially extend the street parking closure for everyone, so please be courteous of these temporary restrictions. Additionally, temporary no parking signage will be posted in this area.

  • Power Washing, Cleanup, & Caulking: The concrete crew continues to power wash garages and houses after work is complete; please be patient, as this process can take a few days to occur after the concrete has fully cured and is drivable again. Downspouts and landscaping impacted by the concrete work in all areas will also be repaired over the next few weeks. Final touch caulking will take place in the next several weeks and could temporarily impact garage access for a few hours; more details coming on this impact soon.

  • Trash Cans: If your alley is inaccessible due to the concrete work, your trash cans can be set out on 11th or 10th Place (east-west streets) for Waste Management to pick up.

Concrete Schedule Update - 11/8

  • Area 10: This area was poured Thursday (11/4) and is expected to be ready to drive on again Monday afternoon (11/8).
  • Area 11: Demolition work will begin in Area 11 on Monday (11/8), with the Area 11 alley tentatively scheduled to open to vehicles again on 11/15 (depending on weather). This means no vehicles in the alley and no alley-side garage access from 11/8-15. Demo and removal work is expected to take about two days, with prep work planned for Wednesday (11/10) and a concrete pour tentatively scheduled for Thursday (11/11). Soils testing and weather both have the potential to impact this timeline, and any updates will be communicated via email.
  • Areas 8 & 9: Areas that do not impact garage access will be demoed starting next Friday (11/12) with a concrete pour planned the week of 11/15. For areas that will impact garage access, demo will begin the following Monday (11/15) with garage access available again one week later (11/22). 
  • Advance Notice - Depew Parking Closures: Some parking on the east side of Depew Street between W 10th Place and W 10th Ave will be impacted by the concrete work. Parking is tentatively expected to be temporarily closed in this area early the week of 11/15 for about three days to make room for the equipment needed for this work. An updated timeline will be sent as we get closer to the week of 11/15.

  • Power Washing, Cleanup, & Caulking: The concrete crew continues to power wash garages and houses after work is complete; please be patient, as this process can take a few days to occur after the concrete has fully cured and is drivable again. Downspouts and landscaping impacted by the concrete work in all areas will also be repaired over the next few weeks. Final touch caulking will take place in the next few weeks and could temporarily impact garage access for a few hours; more details coming on this impact soon.

  • Trash Cans: If your alley is inaccessible due to the concrete work, your trash cans can be set out on 11th or 10th Place (east-west streets) for Waste Management to pick up.

 

Concrete Schedule Update - 11/1

  • Area 7: This area will be ready to drive on again Tuesday (11/2) instead of today (11/1) due to concerns that the concrete has not cured enough to take vehicle weight without potential cracking. Thank you for your patience.
  • Area 10: Demolition work began in Area 10 today (11/1), with the Area 10 alley tentatively scheduled to open to vehicles again on 11/8. This means no vehicles in the alley and no alley-side garage access from 11/1-8. Concrete demo and removal is expected to take several days, followed by a concrete pour on Thursday (11/4). Soils testing and weather could have an impact on this timeline; additional information will be shared as it becomes available.
  • Area 11: Demolition work will begin in Area 11 the following Monday (11/8), with the Area 11 alley tentatively scheduled to open to vehicles again on 11/15 (depending on weather). This means no vehicles in the alley and no alley-side garage access from 11/8-15.
  • Saw Cutting on the East Side of WLV: Saw cutting is a type of preparatory work done in advance of concrete demolition to ensure that the correct portions of concrete are extracted. You can expect to see the saw cutter in your area in advance of the designated demolition day, as well as after the concrete has been poured so joints can be cut into the concrete. The pre-demo work does not cause garage access issues; if a worker is in your way, please just ask them to move.
  • Trash Cans: If your alley is inaccessible due to the concrete work, your trash cans can be set out on 11th or 10th Place (east-west streets) for Waste Management to pick up.

  • Advance Notice - Depew Parking Closures: Some parking on the east side of Depew Street between W 10th Place and W 10th Ave will be impacted by the concrete work as crews move to replace the sections identified in Area 8. The areas impacted and associated timeline are coming soon.

 

Concrete Schedule Update - 10/29

  • Area 7: This area will be ready to drive on again Monday afternoon (11/1). The currently demoed sidewalk area between Areas 7 and 5 will be poured sometime next week, as this section failed the required soils testing today.
  • Area 10: Demolition work will begin in Area 10 on Monday (11/1), with the Area 10 alley tentatively scheduled to open to vehicles again on 11/8 (depending on weather). This means no vehicles in the alley and no alley-side garage access from 11/1-8. Concrete demo and removal is expected to take two days, followed by a concrete pour on Wednesday (11/3) or Thursday (11/4).
  • Area 11: Demolition work will begin in Area 11 the following Monday (11/8), with the Area 11 alley tentatively scheduled to open to vehicles again on 11/15 (depending on weather). This means no vehicles in the alley and no alley-side garage access from 11/8-15.
  • East Side of Depew Schedule Change Rationale: The timeline for the eastern side of Depew sections of the project have been moved up because the increased risk of weather delays later in the season is likely to have a bigger impact on the large concrete slabs in the alleys (Areas 10 and 11) than the smaller sidewalk/stoop work in Areas 8 and 9. The new order of the areas on the east side of Depew will be: Area 10, 11, 9, then 8 (new dates coming soon for Areas 9 and 8, which may be combined into the same week).
  • Saw Cutting on the East Side of WLV: Saw cutting is a type of preparatory work done in advance of concrete demolition to ensure that the correct portions of concrete are extracted. You can expect to see the saw cutter in your area in advance of the designated demolition day, as well as after the concrete has been poured so joints can be cut into the concrete. The pre-demo work does not cause any garage access issues; if a worker is in your way, please just ask them to move.
  • Power Washing & Cleanup: The concrete crew continues to power wash garages and houses after the concrete is completely cured; please be patient, as this process can take a few days to occur after the concrete has fully cured and is drivable again. Downspouts and landscaping impacted by the concrete work in Areas 1-7 will be repaired after the concrete work on the west side of Depew Street is completed, and the downspouts and landscaping will be repaired after Areas 8-11 on the east side of Depew Street have been completed.
  • Advance Notice - Depew Parking Closures: Some parking on the east side of Depew Street between W 10th Place and W 10th Ave will be impacted by the concrete work as crews move to replace the sections identified in Area 8. The areas impacted and associated timeline are coming soon.

 

Concrete & Area 10/11 Schedule Update - 10/28

**Note the upcoming early demo dates for Areas 10 and 11.**

  • Area 6: The second (eastern) portion of Area 6 was poured Monday (10/25); this area should be ready to drive on again later today (10/28).
  • Area 7: The grey concrete is expected to be poured today (10/28), with the colored concrete pour scheduled for Friday (10/29). Plastic will be used to divide the different colors and will be removed after the concrete pours are complete. The goal is for this area to be drivable again the following Monday (11/1); please be aware that soil conditions and/or weather could slow down the process.
  • **Areas 10 & 11 - EARLY Demo!**: Demolition work will begin in Area 10 on Monday (11/1), with the Area 10 alley tentatively scheduled to open to vehicles again on 11/8 (depending on weather). Demolition work will begin in Area 11 the following Monday (11/8), with the Area 11 alley tentatively scheduled to open to vehicles again on 11/15 (depending on weather). In both cases, demo/removal is expected to last two days, followed by a concrete pour later in the week. The timeline for these sections of the project have been moved up because the increased risk of weather delays later in the season is likely to have a bigger impact on the large concrete slabs in the alley than the smaller sidewalk/stoop work in Areas 8 and 9. The new order of the areas on the east side of Depew will be: Area 10, 11, 9, then 8 (new dates coming soon for Areas 9 and 8).
  • Temporary road closure / parking changes on west side of W 10th Place: The western half of W 10th Place from Depew Street to the alley in front of 5654 W 10th Place will continue to be closed from 7 am to 6 pm today (10/28) and tomorrow (10/29). There will also be no street parking allowed in this area during this time. These measures are in place to protect your vehicle, as the concrete crew will be maneuvering large pieces of equipment into a small space and need the extra space to complete the complex pours in Area 7.

Map & FAQs Link: https://sheridanstationwestmd.colorado.gov/sites/sheridanstationwestmd/files/documents/Concrete%20Repair%20Work%20FAQs_1.pdf

Concrete Update - 10/26

  • Temporary parking changes on west side of W 10th Place: Last week we announced that there will be a few daytime closures of the western half of W 10th Place this week. After further evaluation, the concrete crew has opted to temporarily close the western half of W 10th Place from Depew Street to the alley in front of 5654 W 10th Place from 7 am to 6 pm on Wednesday (10/27) - Friday (10/29). There will also be no street parking allowed in this area during this time. These measures are in place to protect your vehicle, as the concrete crew will be maneuvering large pieces of equipment into a small space and need the extra space to complete the complex pours in Area 7. Vehicles are welcome to park in the two legally designated spots on W 10th Place outside of the 7 am to 6 pm designated work hours. Garage access on W 10th Place will not be impacted by this temporary street closure.
  • Area 6: The second (eastern) portion of Area 6 was poured yesterday (10/25); this area will be ready to drive on again Thursday (10/28). The unexpectedly wet soil under this area slowed down the removal of the concrete in Area 6, so thank you for your patience with the reopening of this alley.
  • Area 7: Demo started in Area 7 yesterday (10/25) and will continue today (10/26). The grey concrete will be poured on Wednesday (10/27) or Thursday (10/28), and the colored concrete will be poured on Thursday (10/28) or Friday (10/29). Plastic will be used to divide the different colors and will be removed after the concrete pours are complete. The goal is for this area to be drivable again the following Monday (11/1); please be aware that soil conditions and/or weather could slow down the process. We will keep you updated with any changes to the timeline.
  • Power Washing & Cleanup: The concrete crew continues to power wash garages and houses after the concrete is completely cured; please be patient, as this process can take a few days to occur after the work has been completed. Downspouts and landscaping impacted by the concrete work in Areas 1-7 will be repaired after the concrete work on the west side of Depew Street is completed.
  • Trash Cans: If your alley is inaccessible due to the concrete work, your trash cans can be set out on 11th or 10th Place for Waste Management to pick up.

Map & FAQs Link: https://sheridanstationwestmd.colorado.gov/sites/sheridanstationwestmd/files/documents/Concrete%20Repair%20Work%20FAQs_1.pdf

Concrete Update - 10/22

  • Area 5: All portions of area 5 are ready to be walked on; driving will be opened up again on Saturday (10/23).
  • 5648 W 11th Place: The concrete repair is complete and ready to be driven on again.
  • 1076 Eaton Place: The stoop has completed curing and is ready to be walked on again.
  • 1061 Eaton Place: The stoop has been demoed, and due to a shortage of extra materials from the Area 6 pour yesterday it will not be poured until Monday (10/25). A ramp will be moved into place to facilitate front door access in the meantime. Once the concrete is poured, it will be ready to walk on again in 24 hours.
  • Area 6: The unexpectedly wet soil under this area slowed down the removal of the concrete in Area 6. The first (western) portion of Area 6 was poured on Thursday (10/21) and will be available to drive on again Monday (10/25). The second (eastern) portion of Area 6 will complete demo today (10/22) and be poured on Monday (10/25); this area will be ready to drive on again Thursday (10/28). Thank you for your patience with the delayed timeline, as soil conditions are difficult to predict.
  • Area 7: Demo will start in Area 7 on Monday (10/25) and continue into Tuesday (10/26). The grey concrete will be poured on Wednesday (10/27) or Thursday (10/28), and the colored concrete will be poured on Thursday (10/28) or Friday (10/29). Plastic will be used to divide the different colors and will be removed after the concrete pours are complete. The goal is for this area to be drivable again the following Monday (11/1); please be aware that soil conditions and/or weather could slow down the process. We will keep you updated with any changes to the timeline.
  • West Side of W 10th Place: There may be a few short (1-2 hour) daytime closures of the western half of W 10th Place Wednesday (10/27) - Friday (10/29) to allow space for the concrete trucks to stage the Area 7 concrete pours.
  • Trash Cans: If your alley is inaccessible due to the concrete work, your trash cans can be set out on 11th or 10th Place for Waste Management to pick up.

10/19 Concrete Update

  • Area 5: The remaining portions of Area 5 will be poured tomorrow (10/20). Driving access will be restored on 10/23 (Saturday) in the late afternoon. The pour in this area was delayed due to a failed soils test earlier today, but the area has now passed and is ready for the pour tomorrow. 
  • 1061 Eaton & 1075 Eaton: Demo on these front stoops will finish up and these areas will be poured tomorrow (10/20). No garage access on these units will be impacted, and these areas can be walked on after 24 hours of curing time.
  • 5648 W 11th Place: This garage-side concrete repair is now curing and will be drivable again on 10/22 (Friday) in the late afternoon. All other alley access in this area will remain open throughout this repair. 
  • Area 6: Demo started today (10/19) and will continue tomorrow (10/20). This area will be poured on 10/21 (Thursday) or 10/22 (Friday) and should be available to drive on again starting on 10/25 (Monday) in the late afternoon.
  • Area 7: Demo will start on 10/25 (Monday). More details coming soon on how the two colors of concrete will be handled, as this is slightly more complicated with respect to timeline.
  • General Notes: There may be some construction equipment in and out of the alleys to the north of Area 6 to facilitate the completion of the demolition and pour for the Area 6 alley. Please just ask the construction workers to move if you need to get out of your garage and they will do their best to move as quickly as possible.

Thank you again for your patience as this project continues! We will continue to provide updates as soon as we receive additional information, as soils testing, material availability, and the weather all have an impact on the timelines for the concrete replacement.

Map & FAQs Link: https://sheridanstationwestmd.colorado.gov/sites/sheridanstationwestmd/files/documents/Concrete%20Repair%20Work%20FAQs_1.pdf

 

10/18 Concrete Update

  • Area 5: The remaining portions of Area 5 will be demoed today (10/18) and poured tomorrow (10/19). Driving access will be restored on 10/22 (Friday) in the late afternoon.
  • 1061 Eaton & 1075 Eaton: These front stoops will be demoed today (10/18) and poured tomorrow (10/19). No garage access on these units will be impacted, and these areas can be walked on after 24 hours of curing time.
  • 5648 W 11th Place: Garage access will be demoed today (10/18) and poured tomorrow (10/19) to facilitate a small concrete repair. 1060 Eaton Street garage access may also be impacted, as the repair work will extend to the middle of the alley. All other alley access in this area will remain open throughout this repair. This area will be drivable again on 10/22 (Friday) in the late afternoon.
  • Area 6: Demo will start 10/19 (Tuesday) - demolition will progress from west to east. This area will be poured on 10/21 (Thursday) or 10/22 (Friday) and should be available to drive on again starting on 10/25 (Monday) in the late afternoon.
  • Area 7: Demo will start on 10/25 (Monday). More details coming soon on how the two colors of concrete will be handled, as this is slightly more complicated with respect to timeline.

Map Link: https://sheridanstationwestmd.colorado.gov/sites/sheridanstationwestmd/files/documents/Concrete%20Repair%20Work%20FAQs_1.pdf

October 15 Update

Concrete Update

  • Area 3: There will be a small repair made to a small concrete area on the west side of 5648 11th Place on Monday (10/18). As a result, 5648 W 11th Place will be inaccessible via the garage side from Monday morning (10/18) until Friday morning (10/22). 1060 Eaton Street garage access may also be impacted, as the repair work will extend to the middle of the alley. All other alley access in this area will remain open throughout this repair.
  • Area 4: The concrete is curing and this portion of the alley will be open again by no later than Monday morning (10/18).
  • Area 5: The first portion was poured today, and the rest will be demoed and poured on Monday and Tuesday (10/18-19). The areas poured early next week should be available to drive on again by late Friday (10/22).
  • Area 6: Demo is still expected to start on Wednesday (10/20). More info on an updated timeline coming soon!
  • Area 7: The concrete contractor is working on a revised timeline for this area, as two separate colors of concrete will need to be demoed and poured. More info coming soon!

Map Link: https://sheridanstationwestmd.colorado.gov/sites/sheridanstationwestmd/files/documents/Concrete%20Repair%20Work%20FAQs_1.pdf

Thank you for your patience as we continue to progress through this project, and hope you have a great weekend!

October 12 Update

Concrete Update

  • Area 4: The rain today caused some soil issues that delayed the scheduled concrete pour. The construction crew is planning to pour this area on 10/13 (Wednesday). The upcoming cold weather is likely to extend the curing time needed for this section, so residents in this area should expect to have alley-side access restored on 10/18 (Monday). 
  • Area 5: The construction crew split Area 5 into alternating sections to ensure access to homes is maintained as much as possible in light of potential upcoming delays as inclement weather moves into our area later this week. The first concrete pour is scheduled for 10/14 (Thursday) or 10/15 (Friday), with a second pour planned for 10/18 (Monday) or 10/19 (Tuesday). The incoming inclement weather may have an impact on this schedule, and we'll continue to send the latest information as it becomes available.
  • Area 6: Demo is expected to begin on or around 10/20 (Wednesday). This area will likely be split into two sections to facilitate access to homes - more to come as additional details are received.

October 11 Update

Concrete Update

  • Area 5 - early demo on 10/12: In an attempt to get ahead of inclement weather headed our way later this week, demo is now being moved up one day to 10/12 (Tuesday). Demo is expected to take part of Tuesday and Wednesday, with a pour planned for Thursday or Friday depending on weather. This area should be ready to drive on again by 10/18 (Monday) - again, this is assuming that the weather holds and we will provide updates as they become available. 
  • Area 4: Demo of this area is now complete, and is expected to be poured on 10/12 (Tuesday). This area should be ready to drive on again by late 10/15 (Friday).

The construction team will continue to prioritize completing areas as quickly as possible to maximize access to garages. Thanks again for your patience, and we will continue to send scheduling updates your way as they become available. 

Map Link: https://sheridanstationwestmd.colorado.gov/sites/sheridanstationwestmd/files/documents/Concrete%20Repair%20Work%20FAQs_1.pdf

 

October 7 Update

Concrete Update

Thank you again for your continued patience as the concrete project continues! The latest updates on the schedule are listed below. Please note that soil testing, material shortages, and/or inclement weather could impact the estimated timelines. We will continue to provide updates as they become available.

  • Area 1: The north portion of the alley and Eaton street should be ready to drive on as of 10/7 (Thursday) or 10/8 (Friday).
  • Area 2: The north end of the alley and sidewalk is expected to be poured on 10/7 or 10/8 and should be available to drive on as of 10/12 (Monday). The portion that has already been poured should be ready to drive on late 10/8 (Friday).
  • Area 3: The south portion of the alley is expected to be poured on 10/7 or 10/8 and should be ready to drive on as of 10/12 (Monday).
  • Area 5a: The sidewalk on the north side of 10th Place will be poured on 10/7 or 10/8.
  • General Cleanup: The concrete contractor will use 10/8 (Friday) as a general cleanup day. Concrete splatters will be power washed from houses adjacent to areas that are completely cured.

Upcoming Work Next Week

  • Area 4: Demolition will begin on 10/12 (Monday), with concrete pouring expected on or around 10/13.
  • **Area 5b: The driveway and sidewalk on the south side of 10th Place will be demolished on or around 10/15 (Wednesday), with concrete pouring expected on or around 10/16. Note that this demolition date is several days ahead of the original schedule for this section, and it is possible that this date may be pushed back due to inclement weather that is currently forecasted for next week.

Map Link:  https://sheridanstationwestmd.colorado.gov/sites/sheridanstationwestmd/files/documents/Concrete%20Repair%20Work%20FAQs_1.pdf

 

October 6 Update

The sidewalk on the north side of W 10th Place will be demoed today (10/6) - this is ahead of the original schedule for the rest of Area 5. However, the remaining portions of Area 5 remain on the original timeline, so no driveways/garages are impacted by this demo.

October 4 Update

There are a few upcoming concrete replacement schedule changes that will impact the following areas:

  • Area 2: This area will be poured starting on 10/5. It will be a three-day cure period before cars are allowed to drive on this section, which is an extension to the original timeline.
  • Area 3: The alley portion of this section will undergo demolition on 10/5 and 10/6 instead of next week as originally planned. This means that the entire alley will be inaccessible for a few days due to Area 1 still curing - please note that this also means that access will not be available to garages sandwiched in between Area 1 and Area 3 (5656 W 11th Place, 5652 11th Place, 1068 Eaton Street, and 1064 Eaton Street).
  • Area 4: 5622 W 11th Place and 1063 Depew Street will now be included as part of the Area 2 schedule since those segments were unexpectedly demoed this morning. Otherwise, the rest of Area 4 is expected to start on 10/12.
  • Additional Work: 1061 Eaton Street's stoop will be added to the Area 5 work.

Also, we have a few updates on areas that have already been poured:

  • Area 1: Concrete has been poured and will be ready to drive on after three days of curing.
  • Driveways on Eaton Street (1057, 1061, 1077): These driveways will be ready to drive on today; thanks again for your patience with the demolition of these areas starting much earlier than originally planned!

Thank you for your continued patience as the concrete project continues. While inclement weather could delay the project, the contractor is moving as quickly as possible and we will continue to provide scheduling updates as they become available.

September 22 Update

The concrete contractor did not follow the agreed-upon project timeline yesterday. The published schedule is still planned to be followed going forward as much as possible, but the concrete contractor's unplanned decision to start on the wrong portions of the project may require that there are additional adjustments to the schedule. There will be representatives on site today to assess next steps, and we will send out updates as they become available. Thank you for your patience.

September 22 Update, Part 2

We have a few additional concrete-related updates for you this afternoon:

Area 3 Driveways on Eaton: If your driveway was part of the unplanned work yesterday in Area 3 and your car is currently stuck in your garage, please let me know ASAP so arrangements can be made to get your car out via a temporary dirt ramp. Concrete will be poured in those areas Wednesday or Thursday depending on when soil moisture requirements are met. These driveways will be following the Area 2 timeline on the published schedule.

Area 4 Alley: Area 4 was saw cut yesterday, but removal and replacement with access restrictions to garages is expected to follow the timeline linked below.

General Access: Saw cutting will continue around the neighborhood; however, this is not expected to cut off access to your garage (though you may have to wait for equipment to be moved). If you encounter any issues with the construction crew not allowing you access during saw cutting, you can contact DIRC Homes Superintendent Tim Jones at (720) 380-7267 for assistance.

Schedule Link: https://sheridanstationwestmd.colorado.gov/sites/sheridanstationwestmd/files/documents/Concrete%20Repair%20Work%20FAQs_1.pdf